Polka Dots & Rosebuds Interiors |
There is no “standard” kitchen renovation timeline simply because every kitchen is a different size and renovation needs vary. You have to factor in the availability of the sub-contractors (electricians, plumbers, etc). Ideally you can line them up back to back, but it rarely works out perfectly, so expect a couple days of downtime where no work is being done on your project.
Polka Dots & Rosebuds Interiors |
If you have all your selections made and materials ordered before demo begins, a project could be completed in as little as 6 weeks. If there are a lot of custom elements, walls torn down, plumbing moved, or hiccups in the project it could take as long as 3 months.
Polka Dots & Rosebuds Interiors |
Typically, cabinets take 4 weeks to manufacture. When having custom cabinets made, the timeline can increase to 12 weeks or more, depending on the workload of the carpenter.
Most materials, such as tile, take 3 weeks from order to delivery, assuming the stock is good.
Granite takes 2-3 weeks from template to installation. The template cannot take place until your cabinets have been installed.
Polka Dots & Rosebuds Interiors |
When talking with your contractor about the timeline of the project, add 2 weeks to the total timeframe. This is simply to offer a buffer in case of any surprises found along the way. Surprises could be anything from materials being backordered, to discovering the wall you want to tear out has an HVAC vent running through it, to ripping up the floor and finding rotten floor joists. Building codes also offer challenges in the renovation process. What may have been up to code when your house was built, may now be out of date and require some changes while you are renovating (think plumbing and electrical).
No comments:
Post a Comment